The approved construction hours are Monday to Friday from 7am to 6pm, and on Saturdays from 8am to 1pm.
Any planned works outside of these hours will be communicated in advance.
Access to the shared southern path on the riverbank between Wilde Avenue and Church Street is closed for the duration of the project for the safety of pedestrians, cyclists and workers.
The existing staircase on the southern side of Barry Wilde Bridge on Wilde Avenue is also now closed to enable construction activity.
Pedestrian access is maintained via Phillip Street and George Khattar Lane.
The project is committed to minimising the impact of works, including keeping noise, dust and vibration to a minimum. All construction activities are carried out with the health and safety of the local community as our top priority, and in accordance with the approved construction management plans.
We are committed to keeping the community informed and regular updates will be provided.
Minimising our environmental impact and reducing unwanted mail is important to us. A ‘digital first’ approach for the distribution of communication material is being adopted.
8 September 2023
From a new date of 17 September 2023, activity is required on Phillip Street, at the intersection of Wilde Avenue, to enable water services into the site.
5 September 2023
The Powerhouse Parramatta project modification two is currently on public exhibition for 2 weeks from 1 September 2023.
31 August 2023
On 7 September 2023 final works will take place to complete installation of services to the new site accommodation on Dirrabarri Lane.
4 June 2023
Activity is required on Phillip Street, at the intersection of Wilde Avenue, to enable water services into the site.
29 May 2023
Site accommodation and overhead protective hoardings will be installed in Dirrabarri Lane.
25 January 2023
Out of hour steel deliveries will arrive to site over the year from approximately 30 January 2023.
14 December 2022
The Powerhouse Parramatta construction site will be closed for the December/January holiday period from Friday 23 December 2022 and re-open Wednesday 4 January 2023.
7 December 2022
Tower crane 3 is scheduled to be established in 2 stages from Monday 12 December 2022 to Saturday 7 January 2023.
2 December 2022
Night works to install and commission new pipework required to supply water to the project site is scheduled from 12 to 16 December.
7 November 2022
Tower crane 2 will be established from 14 November to assist with the movement of heavy materials on site.
2 September 2022
Endeavour Energy will be carrying out essential maintenance between 10 and 11 September and power supply will be interrupted.
26 August 2022
Tower crane 1 will be established from 1 September. Three free standing tower cranes will be installed on site to assist with the movement of heavy materials on site.
16 August 2022
Piling equipment will be demobilised over 2 separate occasions via George Khattar Lane.
13 July 2022
A new temporary footpath is being installed from the riverfront pathway to the existing pathway on George Khattar Lane.
10 May 2022
Stormwater services diversions are taking place on the western side of Wilde Avenue at the intersection of Phillip Street.
30 April 2022
Fredon will be completing electrical upgrade night works on Phillip Street between 2 and 13 May.
14 April 2022
The Powerhouse Parramatta construction site will be closed for the Easter break from Friday 15 April and re-open Wednesday 20 April.